Staff Resource Planning Using ASTA

1 reply [Last post]
Joseph McCluskey
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 29 Jun 2012
Posts: 5
Groups: None

Hi All,

I have been tasked with creating a site staff resource programme by my employer.

I am relatively new to planning and am hoping someone could provide me with suggestions on how to efficiently create a programme for staff resources using ASTA.

The objective of the programme is to view working time against non productive time to assign excess capacity to jobs.

Any assistance would be greatly appreciated.

Thanks

Joe

Replies

Mike Testro
User offline. Last seen 44 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Joseph

Set up a series of task hammocks that contain the scope of work for each staff resource. For instance if you are employing an MEP supervisor then add all the MEP tasks to the hammock and then add the Supervisor resource to the hammock.

The same with other trades such as Groundworks - concrete - finishings etc.

Staff that are going to be on site full time add to the project Level 1 summary.

Best regards

Mike Testro