Re-schedule

4 replies [Last post]
Ronan Niland
User offline. Last seen 7 years 51 weeks ago. Offline
Joined: 21 Jun 2012
Posts: 10
Groups: None

After I press F9 to re-schedule a box appears on the screen, asking what date to straighten the progress line to. I turned that box off, and now I want to turn it on again. How do I do this ??

 

Thanks 

 

Ronan

Replies

Ronan Niland
User offline. Last seen 7 years 51 weeks ago. Offline
Joined: 21 Jun 2012
Posts: 10
Groups: None

V 11

Yasin Vural
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 7 Jul 2012
Posts: 5
Groups: None

Ronan Niland, are you using v11 or v12? 

Chris Rymer
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 11 Jun 2010
Posts: 32
Groups: None

Ronan

To turn the dialogue box back on (in Version 12) go to File - Options - General. On the right hand side is a button called Do not show again prompts.... Click on this and select the Reset button. This will will restore the box you are after.

Regards

Chris Rymer

 

Mike Testro
User offline. Last seen 32 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Ronan

There are two sets of adjustments - assuming you are using the Icons and not that horible ribbon.

1. Tools > Options > Reschedule to set the progres line reschedule date.

2. Format > Barchart > Progress to turn the line display on or off plus other toggles.

Best regards

Mike Testro