Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Powerproject v10.3

1 reply [Last post]
Robert Lenton
User offline. Last seen 13 years 51 weeks ago. Offline
Joined: 28 Feb 2002
Posts: 3
Groups: None
Hi all you Powerproject experts... I’m a new user to this software, having been on MSP for last 10yrs, so not yet fully conversant with any glitches it may have. I am currently updating monthly progress on a large programme file.
On opening up the procurement branch of the programme the tasks have re-ordered themselves, with the summary headers at the bottom of each bank of tasks, instead of at the top as usual, yet the task sequence seems to remain the same!
Anyone know why this has happened, and how a return it back to how it should look without affecting anything?
Your help would be greatly appreciated, as i have to submit it in 2-days, and i need to re-schedule.
Thanks,
Rob.

Replies

Mike Testro
User offline. Last seen 7 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Robert

Asta v 10 has a sort function that is on a hair trigger.

You may have inadvertantly sorted the tasks into date order or similar by double left clicking the column head.

Go to view> Sort> and tick Natural Order and it should come back into line.

Best regards

Mike Testro