#planning #engineer #D&B #planningengineer, al huda engineering works, Egyptian Liquefied Natural Gas (ELNG)

START Date: 
May, 2008
END Date: 
June, 2008
  • Planned, implemented and directed overall project schedules and controls to support the Project Director in managing project review, control and reporting processes and highlight abnormalities in project performance.
  • Devised and executed all aspects of planning and scheduling deliverables of the project including preparation of resource loaded schedules, tracking of actual against baselines, performing variance analysis and updating of weekly/monthly reports at the field and management levels.
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
9000
Experience Hours (Forensic Analysis): 
8500

#planning #engineer #D&B #planningengineer, al huda engineering works, Egyptian Liquefied Natural Gas (ELNG)

START Date: 
May, 2008
END Date: 
June, 2008
  • Planned, implemented and directed overall project schedules and controls to support the Project Director in managing project review, control and reporting processes and highlight abnormalities in project performance.
  • Devised and executed all aspects of planning and scheduling deliverables of the project including preparation of resource loaded schedules, tracking of actual against baselines, performing variance analysis and updating of weekly/monthly reports at the field and management levels.
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
9000
Experience Hours (Forensic Analysis): 
8500

#planning #engineer #D&B #planningengineer, al huda engineering works, Egyptian Liquefied Natural Gas (ELNG)

START Date: 
May, 2008
END Date: 
June, 2008
  • Planned, implemented and directed overall project schedules and controls to support the Project Director in managing project review, control and reporting processes and highlight abnormalities in project performance.
  • Devised and executed all aspects of planning and scheduling deliverables of the project including preparation of resource loaded schedules, tracking of actual against baselines, performing variance analysis and updating of weekly/monthly reports at the field and management levels.
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
9000
Experience Hours (Forensic Analysis): 
8500

VIRALKUMAR PATEL

First Name: 
VIRALKUMAR
Last Name: 
PATEL
Professional Since: 
Jan-2003 (22.8 yrs experience)
Years Experience: 
0

Maintenance Turnaround Planner, in salah gas, in salah gas project

START Date: 
June, 2006

Planner within in salah gas JV(sonatrach-bp-statoil).

schedule Turnaround  activities.

assign resources

produce workpacks

supervise activities during execution phase

produce s curve and 

Experience Hours (Planning & Scheduling): 
24000

Area Planning Engineer, Sicim Kazakhstan, FGP /WPMP

START Date: 
February, 2017

Ø  Main scope includes Engineering, Procurement and Construction work (Temporary facilities, Civil, UG Piping, Electrical, Instrument and Pre-Commissioning).

Ø  Able to understand the Technical Scope of work, Scheduling / Planning the appropriate set of activities and ensuring on timely completion of Project by Operating  Primavera Software.

Ø  Developing of EPC Master Schedule using Primavera P6 Software and updates on weekly basis.

Advisor - Planning and Scheduling, Skanska, PIAS 2 and 4

START Date: 
August, 2000
END Date: 
January, 2002

Field Project Controls assistance for oil & gas projects engineering and construction

Experience Hours (Planning & Scheduling): 
1800
Experience Hours (Cost Management): 
800
Experience Hours (Forensic Analysis): 
500

Rajesh Joshi

First Name: 
Rajesh
Last Name: 
Joshi

SUMMERY (21Years)         

·         Offering 05 years 01 Month of experience at Construction Project Control & Management in Oil & Gas and Petrochemical Sector and 15 years 11 Months (3 Years 1 Month in Gulf) of experience in Building Construction & Infrastructure works.

Professional Since: 
Feb-1997 (28.7 yrs experience)
Oldest experience: 
Feb 1997 (28.7 yrs experience)
Years Experience: 
21

Sr. Project Engineer - Planning, Monitoring and Control, Simplex Infrastructures Limited, 1.International Container Transhipment Terminal (DP World project, Adani group, Cochin, Kerala) 2.Construction of Terminal-II for Mundra Port & SEZ Limited

START Date: 
February, 2005
END Date: 
November, 2008

·         Bid analysis for procurement of bought out item (like pipe spools, cathodic protection, structural fabricated items, materi

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1500
Experience Hours (Forensic Analysis): 
3850

Akhil Chandran

First Name: 
Akhil
Last Name: 
Chandran
  1. The ability to work as part of a team
  2. Good leadership skills
  3. The ability to motivate others and make them aware of an overall aim
  4. Attention to detail
  5. Good communication and interpersonal skills
  6. The ability to see the broader picture and work out how individual elements should operate as part of an overall aim
  7. The ability to remain flexible and calm under pressure and in the face of a tight deadline
  8. Creativity
  9. Good numeracy skills
  10. Good literacy skills
  11. A technical mind
  12. The motivation and desire to sol
Professional Since: 
May-2013 (12.5 yrs experience)
Oldest experience: 
May 2013 (12.5 yrs experience)
Years Experience: 
4

Market Place

No results found... (try selecting a different content filter)