Kazakhstan (AS.KZ)

Tengizchevroil Planner

START Date: 
March, 2008
END Date: 
May, 2009
Tengizchevroil
Sulfur Expansion Project – Planning Analyst
Main Accountabilities:
•Develop and maintain the project schedule/plan.
•Make databases in Access and spreadsheets in Excel. Update these regularly to assist with planning project work and in tracking earned progress against plan. (Man-hours/manpower database was created )
•Weekly recording of productivity / performance of construction contractors based on achieved hours versus expended hours.
•Help plan the works of contractors responsible for project tasks.

PFD Project Controls Engineer

START Date: 
August, 2006
END Date: 
February, 2008
Parsons Fluor Daniel (PFD) - Second Generation Project & Sour and Gas Injection (SGP/SGI) - Planning Progress Technician/Cost Technician
Main Responsibilities:
•Responsible for collecting and analyzing contractor man-hours for inclusion in project manpower reporting system
•Responsible for compiling monthly report
•Assist department supervisor in the preparation of reports for Client
•Assist in preparing project matrices
•Assist in compiling overall progress calculations and statistics
•Assist in any ad hoc reports / exercises requested by management

PFD IT Engineer / Programmer

START Date: 
March, 2005
END Date: 
August, 2006
Parsons Fluor Daniel (PFD) - Second Generation Project & Sour and Gas Injection (SGP-SGI) - Database Support, Application Support
Main Responsibilities:
•Resolutions of all Computer Users Work Station Application & Database help desk requests
•Update of PFD Tengiz Inventory & Asset Register
•Installation, troubleshooting & maintenance of project specific software applications for all project users
•Create Help Desk Tickets for department & users with follow-up for solutions
•Aids Application Support Technician with DBMS

Idil Aksu Project Controls Engineer

START Date: 
March, 2007
END Date: 
November, 2007
Planning & Contract Manager – Mamyr Shopping Mall Project (Almaty, Kazakhstan, Project Budget 30 USD Million)

•     Ability to initiate and promote the function of contract administration
•     Awareness of the processes and activities surrounding Project Cost and Risk analysis
•     Help the business better assign expenses to revenue, and help management know where to cut the deepest with the least impact on revenue

ILF Consulting Engineers Project Controls Engineer

START Date: 
July, 2008
Cost Control Consultant – The 1st stage of the 2nd Phase of the Kazakhstan – China Crude Oil Pipeline Project – ILF Consulting Engineers


•     Prepares procedures for various project control activities including budget preparation, forecasts and related cost engineering
•     Manages cost estimating/forecasting activities including periodic project re-estimates and cost benchmark metrics;
•     Comparing the actual cost against estimated cost at various level of the project

SAMSUNG C&T CORPORATION Singapore Planner

START Date: 
October, 2009
Current Role

WorleyParsons Kz Senior Planner

START Date: 
July, 2008
END Date: 
April, 2009
Senior Planning Engineer
Mining Division / Petrochemical Division (2 months)
Almaty & Atyrau, Kazakhstan
               

Saipem Planner

START Date: 
August, 2009
Current Role

WorleyParsons Kz Planner

START Date: 
September, 2005
Over 3 Years of experience in Project Controls Department working in the petrochemicals in-dustry.

Forensic Planner, Bonatti SpA, Kashagan Field Development Experimental - E&I Project Karabathan

START Date: 
November, 2010
END Date: 
December, 2011

Development of acceleration and recovery schedule, progress reports, assessment of delays and the disruptions during the performance of the works to claim EoT and additional costs.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
1000