Bahrain (AS.BH)

Senior Planner, Alliance Projects, Sugar Refinery

START Date: 
May, 2007

I am working as a senior planning engineer in Bahrain for a large refinery project.

Planning / QS Engineer, Al Moayyed Contracting, Builinding, factories in Bahrain

START Date: 
September, 2002
END Date: 
September, 2004

Estimation, Tendering, post contract management & project planning, for Buildings, office complex and factories.

PLANNING ENGINEER, G P Zachariades(Overseas) Ltd, , RIFFA VIEWS GOLF COURSE DEVELOPMENT - BE5200

START Date: 
October, 2007
END Date: 
March, 2010

Project: Residential villa development (Comprising 350 Luxurious Villas)

RIFFA VIEWS GOLF COURSE DEVELOPMENT - BE5200

Client    : Riffa Views B.S.C (c)

Consultant: MSCEB & Mace International Ltd.

*  Preparing the construction schedule in Primavera P3, and also preparation of other planning documents (like Progress "S" Curve, Earn Value Curve, Man power Histogram etc.).

Document Controller, Terna Contracting WLL, Riffa Views, Ministry Of Housing,

START Date: 
October, 2007

Document ControllerDocument Controller

The Works comprised the construction and completion of luxury villas inclusive of substructure, finishes, electrical, plumbing & mechanical installations, ancillary external works and services within the site boundaries. 

 

Specific duties were:

Priya Rathnakara

First Name: 
Priya
Last Name: 
Rathnakara
1. All Secretarial Work (Arrange conferences, meetings, and travel reservations / flight confirmations for Project Manager). 2.  Document Control & Expedition User 3.  Maintaining Files 4.  Preparation of Daily Manpower and Plant & Equipment Reports. 5.
Professional Since: 
Oct-2007 (17.9 yrs experience)
Oldest experience: 
Oct 2007 (17.9 yrs experience)
Years Experience: 
5

Planning Engineer, Haji Hassan Group, Runway Resurfacing Bahrain International Airport

START Date: 
March, 2006
END Date: 
October, 2007

Duties & Responsibilities

  • Scheduling & Monitoring of the project- recording the progress,
  • Prepare hourly program for critical construction phase.
  • Prepare monthly, weekly, daily look-ahead programs,
  • Prepare Resource Histograms, KPIs,
  • Work out weight factors and generating Progress S-Curve,
  • Identify critical path and critical activities,

 

Projects

  • Runway Resurfacing Project – Bahrain International Airport - $ US 19 million

Senior Planning Coordinator, NMR - Nass-Murray & Roberts Joint Venture, Construction of Arcapita Bank Headquarter & Mosque, Bahrain Bay

START Date: 
November, 2007
END Date: 
June, 2010
  • Scheduling & Monitoring of the project- recording the progress,
  • Prepare monthly, weekly, daily look-ahead programs,
  • Prepare Resource Histograms, KPIs,
  • Work out weight factors and generating Progress S-Curve,
  • What-if analysis,
  • Identify critical path and critical activities,
  • Prepare supporting documents for Delay Analysis.

Sarath Balan

First Name: 
Sarath
Last Name: 
Balan

 

SARATH BALAN                                               

Email: sarathbalan@gmail.com                              

Professional Since: 
Sep-2009 (16.0 yrs experience)
Oldest experience: 
Jan 2010 (15.6 yrs experience, WARNING: 0.3 years variance with Professional Since)
Years Experience: 
3

PLANNING ENGINEER, Bahrain, RAMSIS ENGINEERING, Oil & Gas Field Maintenance Services

START Date: 
March, 2012

 

Activities & Responsibilities:

§  Project Progress Monitoring

§  Scheduling

§  Planning & Intra discipline Co-Ordination

§  Material Management

§  Quantity take-off

§  Performing Delay Analysis

§  Development of Progress Measurement System

Sundar Singh

First Name: 
Sundar
Last Name: 
Singh
Professional Since: 
Jun-1997 (28.2 yrs experience)
Oldest experience: 
Jun 1997 (28.2 yrs experience)
Years Experience: 
43

Market Place

No results found... (try selecting a different content filter)

Syndicate content