Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Mixed use development

Project Controls Engineer, Banu Mukhtar Contracting (Pvt.) Limited, Buildings & Infrastructures, COMMERCIAL & RESIDENTIAL BUILDINGS, Mixed use development, Multiple Projects ; Oil & Gas

START Date: 
September, 2009
END Date: 
April, 2012
  • Construction Planning and Scheduling (Resource & Cost Loaded Master Schedules) using PRIMAVERA 6 & MS PROJECT 2010
  • Identification, monitoring& streamlining of critical paths running through the Project Schedule.
  • Using Earned Value Calculations to monitor project status.
  • Analysing Trends and development of early warning system.
  • Developing Budgets that lead to the establishment of a cost/schedule baseline.
  • Resource and cost management using MS PROJECT & PRIMAVERA.
  • Contractual correspondence

Senior Planning Engineer, Drake & Scull International, Mixed use development

START Date: 
July, 2010

·       Development of Pre- Contract and Post- Contract Program Schedules, Work Breakdown Structures, Project Execution Plan and Method Statements

·       Coordinate with Project Team, Commercial dept., Engineering dept., Procurement dept., to prepare PM Budget, Project Cash Flow and Histograms, Information Required Schedule, Engineering Schedule, Material Submissions and Procurement Schedule

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content