Site Engineer

Site Engineer, Mavani Group of Construction, Marathon Innova, Multistorey Building with 5 Floor Car Parking

START Date: 
May, 2006
END Date: 
October, 2006

ü  Execution of Piling as per soil condition & checking the same upto required depth

ü  Execution of project in given time schedule along with safety & companies standards

Site Engineer, Jyothi Engineering, A P Rayon-Expansion of Pulp production from 300 TPD to 350TPD

START Date: 
January, 1995
END Date: 
March, 1999

·         Actively participated in Mechanical installations and fabrication of steel & carbon steel piping for Pump Mill & Clo2 Plant.

·         Handled the erection of process equipments like drum washer, gas free rotator vacuum, tank ages, and chimney of Soda Recovery Boiler etc.

Site Engineer, AFRINA Trading and Construction , Jumana Tower-Pearl Qatar-Doha-Qatar

START Date: 
August, 2008
END Date: 
November, 2009

• Responsible for supervision finishing works ( Block Works-Plastering-Water Proofing-Ceramic-Painting-Gypsum Board)
• Quantity Surveying of mentioned works for sub-contractors
• Controlling progress of mentioned work activities through daily basis reporting.
• Planning of work activities on a weekly basis plan.

site engineer, private company, maintenance of 3 floors residential building

START Date: 
October, 2004

i have a BS.c. in civil engineering 2004 and now i am a site engineer.

Site Engineer, N/A, Hotel

START Date: 
May, 2009
END Date: 
February, 2011

Site Engineer overseeing groundworks, substructure and superstructure. Duties included general management, procurement, logistics and resolving technical queries.

Site Engineer, Ahmet Aydeniz Co., Aposto-Wondo-Negele Road Upgrading Project Contract-2 IRBA MODA - WADERA ROAD

START Date: 
July, 2010
END Date: 
January, 2011

-          Planning the work schedule of responsible site

-          Preparing the Request For Inspection documents

-          Preparing daily reports

-          Controlling the quality of the works on site

Site Engineer, S.M.Construction,Goa,India, NH – 4 (Pune to Bangalore National Highway) four-way lines Project Package: IV-C (Chain age: 275+000 to 290+000).Davangere to Harihara.

START Date: 
January, 2002
END Date: 
December, 2002

Project:NH – 4 (Pune to Bangalore National Highway) four-way lines Project Package: IV-C (Chain age: 275+000 to

290+000).Davangere to Harihara.

Four way lines work such as Clearing & Grubbing, Embankment, Sub Grade, GSB, WMM, BM and utility ducts, Culverts etc.

Site Engineer, S.M.Constructions,Goa,India, Hemavathy Mini Hydel Project. Gorur, Hassan (dist) Karnataka.

START Date: 
January, 2001
END Date: 
December, 2001

Mini Hydel Project. Gorur, Hassan (dist) Karnataka.

Canal excavation 1.3 Km, Weir, Canal Regulator, Road works, Hume pipe culvert, penstock and Power house and Other Building constructions.

Site Engineer, Tiba Contractors, Multiple

START Date: 
July, 1986
END Date: 
June, 1988

§  Execution of residential buildings including Concrete works and Finishing works

Execution of military factory extension in ABU ZAABAL area

Site Engineer, Alfred McAlpine, Various

START Date: 
December, 1992
END Date: 
December, 1995

Site engineering and site management in relation to various major building projects throughout the UK.  Projects include:

·  Preston Law Courts £25 m

·  Halifax Data Centre £9 m

Responsibilities include:

·  Health and Safety duties (inductions/inspections/method statements/risk assessment/COSHH)

·  Setting out

·  Material take off/orders