Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Revision of Place Concrete from Tue, 2011-06-14 12:20

Barrowing Concrete (m3/hr).

Receive concrete from mixer/lorry direct to barrow, wheel to placing position, tip and return.

 

Distance0 - 10 m2.32
 10 - 20 m1.81
 20 - 50 m1.08

 

As above but including load concrete from deck/tray.                
Distance0 - 10 m0.99
 10 - 20 m0.87
 20 - 50 m0.66
 Extra over to place direct, for dump and shovel in from side, a typical rate of 0.26 hrs/m3.Direct From Ready Mix Lorry (m3/hr).

 

TypeReady MixVia DumperVia Dumper
 Tip DirectTip DirectThrown In
Mass Fill3.122.561.49
50mm Blinding1.271.060.82
Ground Beams ne 0.1 m2 SA1.521.301.00
Ground Beams ex 0.1 m2 SA1.691.491.16
Pile Caps ne 0.1 m2 SA1.161.060.79
Pile Caps ex 0.1 m2 SA2.562.137.69
Duct Walls0.780.710.52
Stub Columns0.430.390.29
Ground Slab ne 155 mm2.131.821.22
Ground Slab 150-300 mm2.331.961.27
Ground Slab 300-500 mm2.562.131.35
Drains, Bed & Cover0.910.850.73

 

 By Lorry Mounted Concrete Pump (m3/hr). 

 

 Thickness -->13.5 m3/hr18 m3/hr
    
Solid Slabsne 100 mm2.172.63
 100 - 150 mm2.442.94
 150 - 200 mm2.633.23
 200 - 300 mm2.863.45
 300 - 500 mm3.233.85
Coffered Slabs 1.641.82
Columns0.5 - 0.10 m21.591.59
 exc 0.10 m21.821.82
Wallne 150 mm1.611.89
 150 - 225 mm1.892.33
 exc 225 mm2.563.23
Independent Beams 1.541.54
Stairs and Landings 1.271.89

 

 

 By Dumper, From Ready Mix Lorry To Position (m3/hr).              
Dumper Capacity -->0.6 m30.8 m31.2 m31.5 m32.3 m3
0 - 20 m10.4114.0818.8225.0033.33
20 - 50 m 9.0912.3616.3922.2229.41
50 - 100 m 7.2910.4113.8818.8625.00
100 - 250 m 5.78 7.8710.0013.5118.18
250 - 500 m 3.65 4.95 8.33 8.9512.35
500 - 750 m 2.16 2.92 4.27 5.43 7.87
750 - 1,000 m - - - 3.97 5.78
 By Tower/Mobile Crane (m3/hr).                                                      
  0.4 m Skip0.6 m Skip0.8 m Skip
Pile CapsSA ne 2 m21.191.391.61
Mass Fill PoursSA 2-5 m31.752.042.33
 ne 10 m33.704.174.76
 10-25 m34.004.550.84
 exc 25 m34.355.005.86
Slabsne 100 mm0.901.091.21
 100-150 mm1.091.311.47
 150-200 mm1.261.531.69
 200-300 mm1.261.531.69
 Exc 300 mm1.381.661.85
Trough & Coffered Slabs 0.951.091.21
Structural Topping ne 100 mm 0.901.091.25
Stairs & Landings 0.640.640.64
Blindingne 150 mm0.881.001.10
BeamsSA 0-0.05 m0.520.580.69
 SA 0.05-0.1 m0.580.650.78
 SA ex 0.1 m0.760.851.02
Wallsne 100 mm0.640.760.88
 100-150 mm0.760.921.05
 150-300 mm0.951.111.28
 exc 300 mm1.101.281.47
ColumnsSA ne 0.05 m20.430.450.48
 SA 0.05-0.1 m20.480.500.54
 SA ex 0.1 m20.510.530.57

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.