Small Scale Spread and Level By Hand
Including load and wheel an average of 20 m from tipped heap (m
3/hr)
Layers ->
|
n.e.25mm
|
25-75mm
|
75.200mm
|
Exc.200mm
|
Sand/Soil
|
|
|
|
|
n.e. 200 m2
|
1.03
|
1.03
|
1.12
|
1.23
|
exc. 200 m2
|
1.37
|
1.37
|
1.49
|
1.64
|
Gravel/Shingle
|
|
|
|
|
n.e. 200 m2
|
-
|
0.86
|
0.93
|
1.03
|
exc. 200 m2
|
-
|
1.14
|
1.23
|
1.37
|
Hardcore
|
|
|
|
|
n.e. 200 m2
|
-
|
0.85
|
1.02
|
1.27
|
exc. 200 m2
|
-
|
1.02
|
1.27
|
1.69
|
Spread and Level By Crawler Shovel
Rates in (m
3/hr)
Machine Bucket->
|
0.6m3
|
0.8m3
|
1.0m3
|
1.2m3
|
Sand/Soil
|
|
|
|
|
n.e. 200 m2
|
18.67
|
38.46
|
43.48
|
52.63
|
exc. 200 m2
|
24.39
|
50.00
|
55.56
|
66.67
|
Gravel/Shingle
|
|
|
|
|
n.e. 200 m2
|
18.87
|
38.46
|
43.48
|
52.63
|
exc. 200 m2
|
24.39
|
50.00
|
55.56
|
66.67
|
Hardcore
|
|
|
|
|
n.e. 200 m2
|
15.87
|
31.25
|
37.04
|
43.48
|
exc. 200 m2
|
19.23
|
40.00
|
47.62
|
55.56
|
Clay
|
|
|
|
|
n.e. 200 m2
|
17.24
|
35.71
|
43.48
|
47.62
|
exc. 200 m2
|
22.22
|
45.45
|
55.56
|
62.50
|