Assistant Planner & Planner, TSP, Templeborough Biomass Power Plant
START Date:
December, 2015 I am using P6 to plan detailed design initgration for civils, structural, architectural, M&E and Highways & Drainage to enable construction of a Biomass Power Plant at Templeborough.
This is a high level project under the Renewable Energy umbrella with a number of stakeholders and sub-contractors.
Experience Hours (Planning & Scheduling):
1550
Experience Hours (Cost Management):
150 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: