Project Management Consultant, ENI Norge, GOLIAT (65 kt Sevan 1000) FPSO Project
START Date:
June, 2011
END Date:
July, 2011 GOLIAT (65 kt Sevan 1000) FPSO Project Consultancy team commissioned to give independent objective project value assurance at Hyundai facilities. Engineering, construction and commissioning schedule forensic and risk analyses. Report, recommendations, benchmarks and presentation.