Worked as a senior contracts aadminstrator for Design &Construction of Underground stations and associated tunnels for Chennai metro Rail at Shenoy Nagar, Anna Nagar East, Anna Nagar Tower, Thirumangalam and cut and cover section (Thirumangalam Ramp) Tamil nadu India.

 

Handled two packages

  • UAA-01
  • UAA-05

I have been extensively involved in forensic delay alaysis for the metro construction by proving the nexus through cause and effect scenarios. I have succesfully proven the quantum of delays and received extension of time of 1 year with compensation on the account of execusable delays. 

  • Used soil profiles at the time of tender/current to ascertain the depth of excavation considered at the time of tender and current i.e to prove the nexus of effect
  • Used cycle time analysis for each dwall panel considerered during tender and compared it against actual to prove the strata changes.
Experience Hours (Planning & Scheduling): 
1600
Experience Hours (Cost Management): 
3000
Experience Hours (Forensic Analysis): 
5550