Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Carillion Construction

Scott Paterson

First Name: 
Scott
Last Name: 
Paterson
Professional Since: 
Feb-2008 (16.2 yrs experience)
Oldest experience: 
Mar 2010 (14.1 yrs experience, WARNING: 2.1 years variance with Professional Since)
Years Experience: 
10

Rob Dean

First Name: 
Rob
Last Name: 
Dean
Professional Since: 
Aug-1992 (31.7 yrs experience)
Oldest experience: 
Apr 2005 (19.0 yrs experience, WARNING: 12.6 years variance with Professional Since)
Years Experience: 
6

Senior Planning Manager, Carillion Construction, Various

START Date: 
March, 2009

Senior Planning Manager responsible for planning and Planners on live civil engineering and rail contracts throughout the country.

Contract Planner, Carillion Construction, London 2012 Olympics International Broadcast Centre

START Date: 
February, 2009
END Date: 
September, 2009

International Broadcast Centre and Media Hub Enabling Works (£2.5m)

Contract Planner for design and construct contract under NEC 3 ECC Contract Conditions. Works located within 2012 Olympic Park to provide enabling works for the construction of the international broadcast studios and press offices.

james tuffin

First Name: 
james
Last Name: 
tuffin

 

I joined Mowlem in 2001 as Section Engineer, working up to Sub Agent shortly after the Carillion aquisition. After completing a project in Bristol, I was asked to produce some tender programmes for the bid team. It was at this stage that I was approached to work as a Contract Planner on a full-time basis.

Professional Since: 
Mar-1997 (27.1 yrs experience)
Oldest experience: 
Feb 2009 (15.2 yrs experience, WARNING: 11.8 years variance with Professional Since)
Years Experience: 
2

Contract Planner, Carillion Construction, Great Yarmouth, Outer Harbour, Scope G

START Date: 
June, 2009
END Date: 
January, 2010

Outer Harbour – Scope G Works (£2.1m)

 

Tender and Contract Planner for construct only contract under FIDIC Conditions of Contract, 4th Edition. Works located at Great Yarmouth Outer Harbour development to provide around 41,000m² hard-standings to create an operation port area. Contract involved the construction of block paving areas complete with electrical ducting, lighting towers 40m in height, approx.

Principal Planner, Carillion Construction, A12 Witham Bypass Phase 2 Major Maintenance and Improvement Works

START Date: 
September, 2009
END Date: 
May, 2010

A12 Witham Phase 2 Major Maintenance (£7.1m)

Principal Planner for construct only contract under NEC 3 Option C contract conditions. Works located on the A12 trunk-road, Witham, Essex to provide re-surfacing and road realignment utilising 24hr working. Contract involved crack and seat re-surfacing techniques, the provision and erection of 2no.

Principal Planner, Carillion Construction, Abberton Reservoir Project 05 - Reservoir Enhancement

START Date: 
May, 2010

Principal Planner for construct only contract under NEC 2 Option C contract conditions.

Works located at Abberton Reservoir, Layer-de-La-Haye, Essex involving enhancements to the existing reservoir to increase its capacity by 58%. This will be achieved by raising the level of reservoir by approx.

jimit shah

First Name: 
jimit
Last Name: 
shah
Professional Since: 
Sep-2006 (17.6 yrs experience)
Oldest experience: 
Jul 2008 (15.8 yrs experience, WARNING: 1.8 years variance with Professional Since)
Years Experience: 
2

Carillion Construction Planner

START Date: 
March, 2010
Current Role

Market Place