Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Valero

Turnaround Planner, Valero, Valero Houston Turnarounds- Unit Crude, ULSD

START Date: 
January, 2011
END Date: 
April, 2011

Turn around project 40 days for Valero Houston refinery, scheduling activities using P6 updating existing schedules, Adding works changes into the schedule and deleting works out of scope, resources leveling, Interface the information between cost department using TTMC cost system as integration tool with SAP and Primavera, and planning department, reporting S-curves per subcontractor, per WO, per WBS as required per management from P6.

Rowdy Hutchins

First Name: 
Rowdy
Last Name: 
Hutchins
Professional Since: 
Jul-1998 (25.7 yrs experience)
Oldest experience: 
May 2008 (15.9 yrs experience, WARNING: 9.8 years variance with Professional Since)
Years Experience: 
2

SUPERVISOR - PROJECTS & TURNAROUND PLANNING SECTION, Valero, Valero Aruba 3 yrs T/A and Capital Projects upgrades refinery from 80,000bbls to 180,000bls/day

START Date: 
November, 2002
END Date: 
December, 2005

MATERIAL COORDINATOR/PLANNER TURNAROUND: Cost Controller, Material Planning and Scheduling for Turnaround. Several Turnarounds and Emergency Shutdowns (for about 60 MMUS$/yr and 900,000 Mhr/ Year) of Crude units, Hydrogen units, Hydrotreater units, Delayed Coker Units, Flare systems, Kerosene unit, Sulphur units, Package Boilers, Turbo Generators, Desalination units and Visbreaker/Vacuum Flasher unit.

Valero Lead Planner

START Date: 
July, 2008
END Date: 
March, 2009
Schedule Lead for $90 MM Capital Projects

Valero Lead Planner

START Date: 
March, 2009
END Date: 
October, 2009
Schedule Lead for $200 MM Capital Project $ ~$50 MM T/A

Valero Planner

START Date: 
May, 2008
Current Role

Valero Planner

START Date: 
October, 2006
Current Role

Larry Reynolds

First Name: 
Larry
Last Name: 
Reynolds
Professional Since: 
Aug-1997 (26.6 yrs experience)
Oldest experience: 
Oct 2006 (17.5 yrs experience, WARNING: 9.1 years variance with Professional Since)
Years Experience: 
0

Valero Planner

START Date: 
August, 2006
Current Role

JORGE SOLORZANO

First Name: 
JORGE
Last Name: 
SOLORZANO
Professional Since: 
Aug-1996 (27.6 yrs experience)
Oldest experience: 
Aug 2006 (17.6 yrs experience, WARNING: 10.0 years variance with Professional Since)
Years Experience: 
0

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content