START Date:
January, 1998
CHLORINE / CAUSTIC REVAMP
Responsible for the PMC supervision of on-site planning and scheduling of the Chlorine / Caustic Revamp Shutdown. The scope of work consisted of the removal and reinstallation of pipework, equipment, steelwork and foundations. The areas involved were a Cell Building, Chlorine Area, Caustic Area, Brine Area, Hydrogen Area and several MCC’s Produced all management graphics and progress reports. All work to be carried out in a two-month shutdown period. Attended weekly progress meetings with the construction team