START Date:
November, 1999
I was a planner working on Sellafield Thorp projects creating detailed project programmes from FEL stages to implementation using MS Project and P3 software. Working on multiple projects I produced programmes and manpower estimates for the following phases whilst reporting on the current phases using critical path analysis and earned value.