Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Project Constraints

7 replies [Last post]
Mahendra Gupta
User offline. Last seen 1 year 8 weeks ago. Offline
Joined: 25 Feb 2020
Posts: 14
Groups: None

There are a number of project constraints that project managers talk about. However, are there any significant constraints that can't be overlooked? If yes, what are they and how to manage them?

Replies

Rafael Davila
User offline. Last seen 1 hour 34 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

No discussion about constraints is complete without talking about resource constraints.

Rafael Davila
User offline. Last seen 1 hour 34 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Please be aware that "similar" constraints work in different ways depending on the software you are using.

Mahendra Gupta
User offline. Last seen 1 year 8 weeks ago. Offline
Joined: 25 Feb 2020
Posts: 14
Groups: None
Yes, it is true that there are a number of project constraints. However, there are six significant constraints that everyone must consider and think of ways to eliminate them. Scope, budget, time, etc.are a few prominent ones. Here is an insightful blog to learn more.

https://www.saviom.com/blog/six-project-constraints-and-ways-to-manage-them/
Patrick Weaver
User offline. Last seen 6 days 19 hours ago. Offline
Joined: 18 Jan 2001
Posts: 373
Groups: None

There are two uses of the word constraint in project scheduling, one is the effect of various limits in the surrounding environment such as resources and finance Zoltan Palffy has a good list in his answer. 

The other is schedule constraints which are various dates imposed on the schedule to influence the analysis (eg, 'start-no-earlier-than').  There are eleven of these listed in my book Easy CPM with a number of variants. Fixed constraints are not recommended, and are prohibited under the DCMA 14 point checklist. 

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

the amount of available time to perform work in itself is a constraint 

the amount of available resources is a constraint

acceptable noise levels while working is a constraint

limited working hours are a constraint 

cash flow is a constraint

fedaral, state and local regulations are a constraint

the supply chain shortage is a constraint

Rafael Davila
User offline. Last seen 1 hour 34 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Santosh Bhat
User offline. Last seen 1 year 3 weeks ago. Offline
Joined: 15 Apr 2005
Posts: 381

There is the traditional triple constraints placed on a project - scope, time and cost. That essentially mean, change one and another needs to change - for example, want something cheaper? then either reduce the scope or take longer to complete the project, but you cna't deliver the same scope for reduced cost and time.

 

Other than that, please elaborate further on your question and we can try helping more.