Step for preparing EPCC Project Schedule and Monitoring method

Member for

14 years 7 months

Hi Najib,

In an EPC Project when you make your project schedule you have to break down the project by WBS (Sometimes Client already prepare the WBS with weighted % and issue it with the tender which has to be used in progress calculation) example ,

Milestone

Engineering

                          You can again break down it by dicipline

Procurement

                          You can again break down it by Long Lead and Bulk which can be then again broken down by dicipline

Construction and Commissioning

                            You can break down it by Area and dicipline or if there is no area then by dicipline

You can measure the,

Engineering by Manhours

Procurement by Cost

Constuction by Cost

Overall progress you can meausre it by Clients terms (if WBS Weighted % in given which is usually WBS based) or by Cost which can give you weighted % for Engineering , Procurement and Construction & Commissioning.

Other seniors can add more detail or you can pop questions to that we can reply.

Warm Regards

Jithin