How to import a project with budgeted man hours

Member for

16 years 3 months

add a column for duration type and change all of your duration types to fixed duration and units/time 

the run a global change 

go to tools global change 

Then New

make sure the top part of the global change where it says Select Subject Area change it to Activity Resource Assignment

make the global change look like this 

where

resource ID Name is not equal to (leave the next part blank)

then 

Calculate cost from units = No 

then on the right select Change 

then on the botom committ

Member for

15 years 9 months

Check if your time period, calendar settings, time units and also resources calendar of your P6. is matching on the imported file  If you want to match the budgeted hours check all your settings.  It could be the imported file is using hours as time unit but your program is days or vice versa. Possible also is your calendar used has the same name as your P6 but different workweek and timeperiods.

Member for

16 years

Friends

Please Answer the above Question???

Regards

Arun