Check if your time period, calendar settings, time units and also resources calendar of your P6. is matching on the imported file If you want to match the budgeted hours check all your settings. It could be the imported file is using hours as time unit but your program is days or vice versa. Possible also is your calendar used has the same name as your P6 but different workweek and timeperiods.
Member for
16 years
Member for16 years
Submitted by Arun Vasanth on Mon, 2011-08-29 16:26
Member for
16 years 3 monthsadd a column for duration
add a column for duration type and change all of your duration types to fixed duration and units/time
the run a global change
go to tools global change
Then New
make sure the top part of the global change where it says Select Subject Area change it to Activity Resource Assignment
make the global change look like this
where
resource ID Name is not equal to (leave the next part blank)
then
Calculate cost from units = No
then on the right select Change
then on the botom committ
Member for
15 years 9 monthsCheck if your time period,
Check if your time period, calendar settings, time units and also resources calendar of your P6. is matching on the imported file If you want to match the budgeted hours check all your settings. It could be the imported file is using hours as time unit but your program is days or vice versa. Possible also is your calendar used has the same name as your P6 but different workweek and timeperiods.
Member for
16 yearsFriends Please Answer the
Friends
Please Answer the above Question???
Regards
Arun