PEP and PQP

5 replies [Last post]
Mike George
User offline. Last seen 17 years 46 weeks ago. Offline
Joined: 2 Jun 2006
Posts: 10
Hi Friends,

I checked out project quality and execution plan but couldn’t find any clear difference. Could you please let me know their difference, actual deffinition and mailing sequence to client.

Best regards
George

Replies

Norzul Ibrahim
User offline. Last seen 16 years 27 weeks ago. Offline
Joined: 17 Dec 2005
Posts: 165
Zhang,

similar to my understanding...
Zhang Haixiang
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
PEP is a document that describe how to manage the project.
It may cover construction management/method, quality control schedule(time control),contract/procurement control, EHS(saftey),document control.

to support the PEP, there will be more detail documents/precedures for each part.
Peter Holroyd
User offline. Last seen 1 week 4 days ago. Offline
Joined: 6 Jun 2005
Posts: 160
to confuse
PIP= PEP + Budget
PEP is basically the method statement for the whole project in written format
Below this document (which can get revised as the project enters new phases) sits a whole raft of more detailed document - one of which is PQP. This should detail the procedures and standards which will be used on the project - anything from design safety to goods received at site to billing the client. The best procedure is of course the one on Auditing of Project Quality and Quality Performance - or doesn’t anybody bother measuring Quality (or more important Quality Failure)any more in ther haste to GET THE JOB DONE ANYWAY?
Norzul Ibrahim
User offline. Last seen 16 years 27 weeks ago. Offline
Joined: 17 Dec 2005
Posts: 165
Based on our experience, PQP will be part of PEP
Norzul Ibrahim
User offline. Last seen 16 years 27 weeks ago. Offline
Joined: 17 Dec 2005
Posts: 165
Project Execution Plan vs Project Quality Plan?