Successor of Substation Works in A Building

1 reply [Last post]
Dura Cell
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 7 Dec 2010
Posts: 32

Hi All,

After the substation works in a Building, what could be the successors or any following activities? 

thanks in advance

Replies

Daniel Limson
User offline. Last seen 5 years 46 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Dura,

Only you can answer such question? normally after you finish E&M installation you need to energize the substation so you can start your T&C, you also need to finish your fitting out works.

Study your scope of works and your BoQ