Physical Percentage Complete

Hi All,

How to get physical percentage complete to rollup upto my wbs and project level?

D
Daniel Limson 👤 Member for 24 years 8 months

Vidhya,

You can use a time base resource by using duration, however, it is not an accurate assessment of physical percentage complete.

When you say physical percentage complete, it should be based on estimated quantities and then converting this to weighted value by using a common unit of measure time or money (Manhours, Mandays or Dollar Value).

Cheers,

Daniel

D
Daniel Limson 👤 Member for 24 years 8 months

Hi Vidhya,

First off, you need to have a common unit of measure (Manhours, Mandays, Dollar or a Weighted Value) broken down to the activity level and loaded to your P6 programme.

Cheers,

Daniel

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts