Physical Percentage Complete

3 replies [Last post]
Vidhya Sagar G R
User offline. Last seen 10 years 49 weeks ago. Offline
Joined: 26 Sep 2012
Posts: 18
Groups: None

Hi All,

How to get physical percentage complete to rollup upto my wbs and project level?

Replies

Daniel Limson
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Vidhya,

You can use a time base resource by using duration, however, it is not an accurate assessment of physical percentage complete.

When you say physical percentage complete, it should be based on estimated quantities and then converting this to weighted value by using a common unit of measure time or money (Manhours, Mandays or Dollar Value).

Cheers,

Daniel

Vidhya Sagar G R
User offline. Last seen 10 years 49 weeks ago. Offline
Joined: 26 Sep 2012
Posts: 18
Groups: None

Hi Daniel,

I am not using any resource into my project.

Daniel Limson
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Hi Vidhya,

First off, you need to have a common unit of measure (Manhours, Mandays, Dollar or a Weighted Value) broken down to the activity level and loaded to your P6 programme.

Cheers,

Daniel