Problem in P6 Resource Usage Spreadsheet and Profile

3 replies [Last post]
Ronn Chester Baluyot
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 33

Hi Guys,

I'm having a problem regarding the resource usage speadsheet and histogram (profile).

I'm experiencing this in my construction program, so i tried it in a one activity program and see if it still exists.

I have an activity with 7 days duration loaded with resource of 70 units linearly distributed. So it means I should have 10 units per day and at the end of the s-curve should have 70 units.

In the spreadsheet, everything is fine and correct. But in the histograme and s-curve it shows only 1 unit (actually it is 1d) and at the end of 7 days the s-curve have 9d. (by the way how to change or remove this "d" units?)

How to correct this problem?

Thanks

Replies

Ronn Chester Baluyot
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 33

Thanks Raymund.

Rungsarit Prombra...
User offline. Last seen 4 years 43 weeks ago. Offline
Joined: 12 Oct 2010
Posts: 12
Groups: None

make sure that you didn't used "calculate average" option

Raymund de Laza
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Ronn,

Check the setting for Resource Distribution Interval in User Preferences. It should match the Timescale display.

Unclick the "Show unit label" in the Preferences.

 

 

Regards,