Resource limit problem in resource usage profile

1 reply [Last post]
Sherif Abdel Moula
User offline. Last seen 11 years 15 weeks ago. Offline
Joined: 19 Feb 2014
Posts: 3
Groups: None

hey, i'm using P6 Professional R8.1, when i check the resource usage profile i find drops in the limit line - limit=Zero - in some working days! my calender has only a weekly vacation on Friday so the limit is dropped to zero in Fridays and that's logical for sure, but i don't know why it's a zero in some working days! i tried to add new resources with new calender where no holidays at all and still the limit line dropped in some days! how can i solve this problem, specially cause i need the resource usage profile printed so they must be correct.

here you're a photo of an example, this zero-limited Monday is a normal 8h working day

2105
untitled.png

 

Replies

Raymund de Laza
User offline. Last seen 41 weeks 2 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hey, the day Mon Sept 05 was set to Non-Working Day.