Hi Folks
Needing a bit of advice on P6 Earned Value calculations. Currently I have my schedule and I note that after updating progress the "earned value" is not calculated for activities that have been added after i set my baseline ( ie. activities where there is no corresponding activity in the baseline). On reading other forums and google it seems that the earned value is calculated using the baseline values and therefore the earned value does not get calculated for my activities that I added later. Can anyone confirm if this is the case or not.
Also I need advice on how to calculate the earned value for these activities that are not in the baseline. Currently I am using user defined fields and doing the calculations myself,using global changes, but surely there must be a way of getting P6 to calculate these earned values accurately.
Any advice will be greatly appreciated.
Thanks
George
Replies