We're currently in the process of getting a baseline approved by the client, and would like to better understand how others get around the use of constraints. Presently we have no constraints in the schedule, but have placed certain activities into the schedule using a positive lag, instead of an ALAP constraint.
Our Client does not want use of constraints, but at the same time they do not want lags. We concur that we do not want any mandatory constraints, but do not want to have preferrential logic ties either as this will mean tying activities to others for convenience and will introduce inaccurate paths through the schedule.
In the old days when P3 a couple of constraints, now in P6 they have added several others, and i fear our Client doesn't fully understand how these additional types work - has anyone ever run into this sort of situation, and how did you overcome the clients reluctance in accepting constraints.