Completion and start dates on P6 schedule

1 reply [Last post]
Amir Pezeshk
User offline. Last seen 12 years 4 weeks ago. Offline
Joined: 5 Dec 2011
Posts: 14
Groups: None

Hi,

For some reason the P6 installed on my laptop calculates start date as finish date completes.  For example:

Activity 1, Duration 4 days, Start January 2, 2012, Finish January 5, 2012 

Activity 2 Start must be January 6, 2012 since it's successor to the Activity 1, but the Activity 2 starts on January 5 same as finish date of .  This is happening on entire schedule.  I have checked User Preferences, and the Calender settings but i cann't understand where the problem is coming from.  Any idea?

Replies

Raymund de Laza
User offline. Last seen 33 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi,

Set the Working Time on your calendar and also show the time on the dates columns to be able to see the problem.

Hope this will help.