Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

BL 1 Start Dates Slip once we assign actual start

1 reply [Last post]
Izam Zakaria
User offline. Last seen 7 years 48 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Guys,

As subjected above, I had problem when I did assign actual start, the BL Start dates will change accordingly.

But this not happen to BL Finish when actual finish had been assigned.

What setting I should do guys?

Replies

Rodel Marasigan
User offline. Last seen 23 weeks 21 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Izam,
When actual start has been tick and data date move the Baseline will slip if the remaining duration was not change. You need to adjust remaining duration to keep the planned finished date if progress was as planned.