BL 1 Start Dates Slip once we assign actual start

1 reply [Last post]
Izam Zakaria
User offline. Last seen 7 years 19 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Guys,

As subjected above, I had problem when I did assign actual start, the BL Start dates will change accordingly.

But this not happen to BL Finish when actual finish had been assigned.

What setting I should do guys?

Replies

Rodel Marasigan
User offline. Last seen 15 hours 40 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Izam,
When actual start has been tick and data date move the Baseline will slip if the remaining duration was not change. You need to adjust remaining duration to keep the planned finished date if progress was as planned.