Help With Out Of Sequence Logic

3 replies [Last post]
Simon Carter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 11
Groups: None

Hi guys,

I'm looking for ideas about syntax to use with Primavera P6 to get all activities with out of sequence logic. We've to activities with FS lag to predecessor that's starting early creating high float. Anyone have any ideas?

Thanks,

Simon

Replies

Simon Carter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 11
Groups: None

Thanks for the help guys...certainly a lot easier than filtering :-)

Simon

Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Let me detail what Gary said.  You need to go to the Schedule Screen (Tools / Schedule menu item or just, F9 Key) and click on the “Log to file” checkbox.  Ensure that the file name listed below is reasonable.  Now click on the Schedule button.

Once done, go back to that same Screen (F9) and this time, click on the View Log button.  This will show you the schedule log.  In there is a section titled, "out-of-sequence activities."  It is not a particularly informative report (the P3 report was much better) but it is better than nothing.  Good luck!

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Simon,

 

Look at your schedule log -this will list all out of sequence activities for you.

 

Cheers,

 