What are Out-of-sequence Activities?

2 replies [Last post]
Emily Foster
User offline. Last seen 3 years 16 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

What exactly is an out-of-sequence activity and why do I care? Learn more http://ow.ly/zx2NU

Replies

Mike Testro
User offline. Last seen 42 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Anand

A simpler more general definition is that Out of Sequence Working is when tasks on a programme are being executed in a different logical sequence to that intended as planned.

This happens on most projects and it should not be ignored but the logic changed to reflect what is actually happening.

Best regards

Mike Testro

Anand Kurmi
User offline. Last seen 3 years 32 weeks ago. Offline
Joined: 10 May 2011
Posts: 4
Groups: None

Hi Emily,

When a successor activity starts earlier than predecessor, out of sequence occurs.

This affects the schedule when progressing update is based on retaine logic.