" Planned Dates"

1 reply [Last post]
Barry Fullarton
User offline. Last seen 33 weeks 4 days ago. Offline
Joined: 6 Jan 2009
Posts: 41
Groups: None

Please can soem one explaine to me what teh function of "Planned Dates" are in P6 and what benfit or use they are best used for ?

Replies

Ronald Winter
User offline. Last seen 3 years 2 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Barry,

 

Planned Dates are your Baseline Dates.  When you display Baseline Schedule bars in the Gantt View, you are showing the other schedule’s Planned Dates.   Be careful what you do with these dates as they have the ability to automatically overwrite other date & duration columns.  Good luck!