How to assign the same baseline to monthly updates?

2 replies [Last post]
j s
User offline. Last seen 12 years 27 weeks ago. Offline
Joined: 11 Oct 2011
Posts: 6
Groups: None

How can I assign the same baseline schedule to my current schedule every month? Right now I make a copy of the baseline schedule and assign it as a baseline to my current schedule which means I have a copy of one baseline for each month. I want to avoid making copies. Is there a way to work around this?

Replies

Simon Willson
User offline. Last seen 2 years 37 weeks ago. Offline
Joined: 1 Dec 2006
Posts: 68

J S,

From reading your post, am I right in assuming that you are making a copy of your schedule each month to update?  Then you are assigning the agreed baseline to the new copy of the schedule?  If this is correct may I suggest that you keep the 'master' copy complete as this will retain the baseline copy.  Prior to you performing your monthly update, if you need to make a backup copy, simply XER a copy to your current schedule to the project archive.  Alternatively, you could save a baseline which will be retained in the EPS with the shedule.  There is no real need to keep making copies to update at the reporting period.  All you end up doing is cluttering (which will eventually impact your performance) up your database with duplicate copies of the same schedule.

 

Regards

 

Simon  

Baris Hazar
User offline. Last seen 7 years 8 weeks ago. Offline
Joined: 4 Dec 2009
Posts: 39

Hi,

There is no such a global baseline option in P6 to be used for all the consecutive updates of a schedule at the same time. You can assign a baseline to a schedule and then unlink it by restoring to use for another one. If you need your baseline attached to all the updates of your schedule simultaneously, you must have copies of it for each schedule.

Regars

 

Baris