Milestones with actual dates for baseline

3 replies [Last post]
Ronn Chester Baluyot
User offline. Last seen 8 years 42 weeks ago. Offline
Joined: 28 Feb 2008
Posts: 33

I'm comparing this months progress and last months progress. I used last month's programme as a baseline for this month's programme and reflect it in the Gantt Chart. So since I'm using last month's programme as a baseline (just for comparison) there are actual dates for tasks and milestones. No problem with task dependent activities, the problem is with the milestones with actual dates. Instead of showing it behind the data date line, it was shown ahead of the data date line just like a planned date. Anyone knows how to solve this. Thanks.

Replies

Ronn Chester Baluyot
User offline. Last seen 8 years 42 weeks ago. Offline
Joined: 28 Feb 2008
Posts: 33

Gary,

That was very helpful. Thak you very much.

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

If you don't have the right settings chosen, Primavera will display planned dates instead of actual for baseline projects.

Check the link below for Paul Harris' excellent explanation of this issue

 

http://www.eh.com.au/Technical%20Papers/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf

 

Cheers,

 

G

Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ron

If a milestone has been reached and achieved you need to set completion at 100%.

Best regards

Mike Testro