Grouping band

2 replies [Last post]
raed hussein
User offline. Last seen 10 years 44 weeks ago. Offline
Joined: 29 May 2007
Posts: 17
Groups: None

if the activities used more than calendar how p6 calculate the variance finish or start for grouping band

Replies

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Durations and, I assume variances also, of grouping bands are calculated using :

  • The Database Default Calendar and
  • The hours/day setting under Edit>User Preferences>Time Units

 

The below links to a presentation by Paul Harris which covers this and other common issues:

http://www.eh.com.au/Technical%20Papers/100602_P6V_%20Bars_Tricks_and_Traps.pdf

Mike Testro
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Raed

As far as I am aware only one calendar can be assigned to a task.

Different calendars can be assigned to resources allocated to the task - in which case chaos reigns.

Best regards

Mike Testro