Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6V7 levels resource actual units

1 reply [Last post]
Alexandre Faulx-B...
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 20 Jan 2003
Posts: 1355
Hello planners, on Activity A, Original Duration 5 days, Resource 1 is working 8 hour/day Activity Actual Start is Monday and Actual Duration 2 days Update Progress on Tuesday night shows Resource 1 Actual Units = 16h, 8 on Monday and 8 on Tuesday On Wednesday night, I schedule the project to show that there was no work at all on Activity A on Wednesday; on the Activity Usage Spreadsheet, P6 shows that Resource 1 worked 5,33 hours per day during 3 days, when I want to read 8 hours per day during 2 days and 0 on Wednesday I cannot find where the setup is Please somebody help! All the best, Alexandre

Replies

Raymund de Laza
User offline. Last seen 31 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi,

That happens because the default resource curve is linear or rectangular.

My advise is use a modified resource curve to control what you wish to define.

Hope this will help.

 

Regards,

 

Raymund