Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Best Practice for construction Progress Measurement , based on cost or Mnahours and WHy?

3 replies [Last post]
Shazia khan
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 21 Apr 2008
Posts: 139

Hi Experts

 

Please advise with your wide range of experience  , caption subject.

 

Thanks

Replies

Dennis Hanks
User offline. Last seen 8 years 1 week ago. Offline
Joined: 17 Apr 2007
Posts: 310

Jose;

I think I agree with your first statement, but not quite sure I understand the second.  Are you saying that eg.  Steel accounts for 20% of our total construction workhours and we are 50% complete (by ton) with steel erection, then we have earned 10% of total construction progress?  If so, then we agree.  The reported construction progress is the aggregate of craft earned hours divided by the total construction workhour budget/estimate.

Workhours 'normalizes' comparison of disparate activities - pipe, wire, foundations, etc. - for earned hours (against established budget/estimate), but not for actual progress, that comes from installed quantities.

Second step is to compare the hours expended to what was allocated, but that was not the question.

Shazia khan
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 21 Apr 2008
Posts: 139

Thanks For your reply.

I  appreciate your advise to measure physical progress based on Qty. ton Mtr. etc.

Construction Progress measurement To calculate the Weight Values for all activity , based on Manhours is easy for me.

Why, M/H based on the Qty ( according to work productivity) (4 Kg/h for Steel fabrication)

Example . if 1000 M/h spent on Fabrication , I can achived the Fab qty 4000 Ton for Steel structure fabrication.

may some other planner using Cost for the same, if they are using Cost then why, they  are not chosing M/H

I want your experience in that.

Thanks so much in advance,

have a nice week end

 

Jose Frade
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None

Good morning Shazia,

It should not be confusion between relative weight of activities to each other (based on cost or M/H) and progress measurement.

Explaining:

Method of measurement for construction should stick allways to physical progress of the works such as Units, m3, klms, tons, etc, done. Then comparing with the total qty to be done it comes a % achieved.

 

Since normaly you have activities with diferent units of physical work (m3, tons, m2, etc) then you have to use the same unit to relative calculate all the progress of the works - therefore MH is the comun unit to give a relative weight to each activity.

 

Summarizing:

M/H - Use as units for work qty and as relative weight of each activity.

Qtys (m3, m2, tons, inches) - Use for physical progress of works.

 

Choosing between M/H and cost: Depends on the kind of projects, activities, etc. Basically boths are suitable.

 

Hope it helps you.

BR

JMFrade