How to load cost

4 replies [Last post]
Gokulakrishnan Ga...
User offline. Last seen 12 years 29 weeks ago. Offline
Joined: 7 Jun 2010
Posts: 19
Hi.. i’m new to P6.. Can any one tell me how to load cost in P6 easily.. In p3 i will create a resource called BOQ and i’ll add this resource to all activities.. then i’ll load the cost as per the break down in the budgeted cost for this new resource.. but in P6 i have just started trying to load the cost..

Replies

Anbin Ponnith
User offline. Last seen 9 years 13 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Hai Gokul
In the Resource Dictonary Please Check the Following Option
1.Select the Resource
1.Units & Price tab- >Price/unit->1.00 (it May be Zero)
2.Details->uncheck the calculate cost from unit
Because in P6 if u assigned a resource it will default assigned a budget unit of (8*orginal duration)
If u run Recalculate Assignment Cost Ur Budget cost will become (Budget unit*Price/unit)
U need to uncheck the calculate cost from units
Recalulate Assignment Cost is Calculated base on Price/Unit*Budget Unit
3.Now if u run Recalculate Assignment Cost I hope it wont Change
4.U need to uncheck the calculate cost from unit for all the resource u have assigned to the project

Regards
Anbin
Gokulakrishnan Ga...
User offline. Last seen 12 years 29 weeks ago. Offline
Joined: 7 Jun 2010
Posts: 19
Thanks Mr.Anbin.. I have used it.. but still i have some confusion that after entering the budgeted cost like as u told & i clicked the recalculate assigned costs in Tools. Then all of a sudden all the budgeted costs i have enterd is changing.. why is it so?..
Anbin Ponnith
User offline. Last seen 9 years 13 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Hai Gokul
In the Resource Dictonary Please Check the Following Option
1.Select the Resource
1.Units & Price tab- >Price/unit->1.00 (it May be Zero)
2.Details->uncheck the calculate cost from unit
Recalulate Assignment Cost is Calculated base on Price/Unit*Budget Unit
3.Now if u run Recalculate Assignment Cost I hope it wont Change

Regards
Anbin
Anbin Ponnith
User offline. Last seen 9 years 13 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Hai Gokul
Try the Following Step if u Want to Type Budget Cost Directly
1.Select Enterprise->Resource Dictionary
2.Resource Id Type BOQ
3.Resource Name (XXXXXX)
3.Resource Type As Material
4.Click ActivityDetail Tab->ResourceTab->Add Resource->Select BOQ(Resource Id)
5.Click Status Tab->Right Corner u Can See Labour unit->Change to Material Cost -> Budget Cost ->type the Cost Directly
Regards
Anbin