Level of Effort

1 reply [Last post]
Oliver Melling
User offline. Last seen 4 years 30 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
Does anyone know how its possible to have a current programme that is on target to meet all baseline dates, but also has level of effort tasks across the project that have less than 1.0 for their SPI?
(This being calculated automatically from duration % complete, all calendars the same)

I have noticed that the at complete duration is greater than the original even though the baseline and current start/finish dates are the same.

Replies

Mike Testro
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Oliver

It seems as though you are using up float.

Best regards

Mike Testro