Budgeted Total Cost Zero after Exporting

1 reply [Last post]
Chris Tan
User offline. Last seen 8 years 47 weeks ago. Offline
Joined: 4 Apr 2010
Posts: 3
Groups: None
Hi All,

After exported P6 file and was found zero budgeted cost in another computer.

Is anyone know how to solve this issue.

Thanks in advance!

Chris

Replies

Rodel Marasigan
User offline. Last seen 8 hours 44 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Chris,
When importing xer from other pc and reaching "Update Project Options" click Modify and make sure under Data Global type-> resource -> Action is Update Existing and not Keep Existing. This will replace Resource already exist on other PC especially for the Rate: Price/Unit.