Resource Assignment Import to P6

2 replies [Last post]
Vaughn Edwards
User offline. Last seen 5 years 32 weeks ago. Offline
Joined: 1 May 2008
Posts: 16
When importing new activities into P6 from excel I can’t assign resource units to an activity. What am I doing wrong. I’ve looked and can’t fine a field to export.

Replies

Rafael Davila
User offline. Last seen 1 hour 40 min ago. Offline
Joined: 1 Mar 2004
Posts: 4781
MOST EASIEST bts Come on kids, it is easy to use, easy to install, we do not need a P6 forum. Vaughn, Perhaps you have no resources defined, in such case you have to import resource definitions before importing resource assignments; otherwise the software might ignore undefined assignments. Sorry this is all I can say as we long ago abandoned use of P3e, the original P6 version. Best regards, Rafael
Mike Testro
User offline. Last seen 3 days 7 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4393
Hi Vaughan

As far as I can see you are doing nothing wrong - as soon as I can download and install the P6 software - no success after 8 days effort - then I may be able to give you better advice.

Best regards

Mike Testro.