How is setting Public Holiday in P6

4 replies [Last post]
mch 714
User offline. Last seen 11 years 48 weeks ago. Offline
Joined: 18 Apr 2008
Posts: 11
The Pubilic holiday and some specific season are how set up calander in P6.

Replies

mch 714
User offline. Last seen 11 years 48 weeks ago. Offline
Joined: 18 Apr 2008
Posts: 11
First I thanks for your reply. My mean is how set holiday on one calander of P6 menu. As example, 1 May of the labour holiday define to no work date and can be appear to every year. it’s no need one by one define it as P3 repeat to every year.
R. Catalan
User offline. Last seen 13 years 21 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
mch 714,

Create 2 calendars:
CAL 1 = working days and public holidays
CAL 2 = Calendar days (all days are working days)

Make CAL 2 as your global calendar.

Best regards,

R. Catalan
Rodel Marasigan
User offline. Last seen 1 week 3 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
mch,

Select Enterprise-> Calendar from Primavera menu. Then select which one you need (Global, Resource or Project) to create. Click Add or modify existing and define it from there.

To assign to activities, Click column icon then under General double click calendar. Click the calendar column and select the calendar you want to assign. Highlight all activities start from the column that you already assign and press Ctrl+E to fill all selected activities.