Summarize BL units % complete

1 reply [Last post]
Aymen BEN YOUSSEF
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 4 Aug 2008
Posts: 23
Groups: None
Hi everybody,

Is there any way to summarize BL units % complete in P6v2?
I’m using only labor units.

Thanks in advance,
Aymen.

Replies

Arnold Puy
User offline. Last seen 9 years 10 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Aymen,

Unfortunately, this is not possible. Only Schedule % complete.

Regards,

Arnold