Calcualtion of duration for a Level of Effort activity

I
Ilgar Akhunduv 👤 Member for 13 years 4 months

I had problem with rescheduling Child  work orders, there was Parent WO with 110 Child WOs after rescheduling them when you press F9 everything goes wrong way, is anyone faced the same problem using P6.

R
Richard Daoud 👤 Member for 16 years 4 months

Hi Ian,

Thanks for your reply.

I got my prblem resolved even without marking the LOE as started.

In fact, the LOE that I wanted to create into my P6 schedule were originally in a MS Project schedule as normal task that have durations and relationships.

At the beginning I tried to import these tasks into P6 from MS Project (in order to save typing time), then I changed their type to LOE and built/modified their relationships but I faced the problem I described (OD=1 always).

Then I tried a differnt way: I exported these tasks to Excel and deleted all data except for the Activity ID and the Activity name, then I imported this Excel sheet into P6, and I made their type LOE and built the relationships. In this way everything was OK.

I think the tip is that when importing an LOE activity we should not import a duration for it.



Regards,

Richard

I
Ian Nicholson 👤 Member for 16 years 4 months

Did you move the data date across the LOE so that the LOE got marked as started? The OD and RD should be the same for a not started activity (unless you have messed with the default settings). P6 has a "feature" that LOEs can get started automatically.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts