P6; Activates Relationships Problem

11 replies [Last post]
Abeer Mahmoud
User offline. Last seen 9 years 1 week ago. Offline
Joined: 8 Jul 2008
Posts: 87
Dear all;
My activities linked by FS; and when I made a schedule I find the following for example;

Activity #1; Start 1/01/2010 Finish 10/01/2010
Activity #2; Start 10/01/2010 Finish 15/01/2010
Activity #3; Start 15/01/2010 Finish 18/01/2010
I wonder why because the normal must be:
Activity #1; Start 1/01/2010 Finish 10/01/2010
Activity #2; Start 11/01/2010 Finish 16/01/2010
Activity #3; Start 17/01/2010 Finish 20/01/2010
I need to solve this problem by the default way, because I solved it by add a lag =1 and I think it is not practical for big projects so can anybody help me by steps.
Best Regards,
Abeer Taher

Replies

Abeer Mahmoud
User offline. Last seen 9 years 1 week ago. Offline
Joined: 8 Jul 2008
Posts: 87
Thanks Alexander;
It worked; I checked detailed work hours/day and made the following:
• From (0) to (7) non work
• From (8) to (15) work
• From (16) to (23) non work
I am very very happy
Best Regards,
Abeer
Dieter Wambach
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Abeer

How are the working hours of the assigned calendar? If an activity is planned until the last minute of a day, the next one will start the first hour of the following day - some constellations with milestones can behave different.

Do you have preferences equivalent to as follows?
Assigned calendar activity 1: Working time 8am to 4pm, activity 2: from 9 am to 5 pm?

Of course you can use different calendars within one project - e.g. Engineering 5d 8h, transport 7d 24h, site 6 d 10h with different holidays. But, to follow Anoon’s words, don’t exaggerate: P6 can deal, but you can’t trace.

Regards

Dieter
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Hi Abeer,

Dieter is right, and I supposed the result of logic depends on how you had defined it.

In your example, one of your activities has 5 days duration and uses a 7 day calendar, is there logic on it?

In my opinion, it is logical to tailor your calendar(s) and resources to your activities (after all, you are assigning resources to activities and not otherwise).

And by the way, use only FS
Abeer Mahmoud
User offline. Last seen 9 years 1 week ago. Offline
Joined: 8 Jul 2008
Posts: 87
Hi Dieter,
I agreed with you about user reference, but I mean I don’t want to face FS problem again in future and for the existing project how can I make
Activity #2; Start 11/01/2010 08:00 Finish 16/01/2010 16:00 (calendar #B; 7 working days 8hrs/day)
Instead of existing; Activity #2; Start 10/01/2010 16:00 Finish 15/01/2010 16:00 (calendar #B; 7 working days 8hrs/day)
Thanks;
Abeer
Dieter Wambach
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Abeer

What do you mean by "by default"? If you’ll work with days you must keep in mind that internally everything will be calculated in hours.
Before you’ll show a report, change your references.

Regards

Dieter
Abeer Mahmoud
User offline. Last seen 9 years 1 week ago. Offline
Joined: 8 Jul 2008
Posts: 87
use one calendar!!!! How come? It is not logic/applicable at all
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
use only one calendar
Abeer Mahmoud
User offline. Last seen 9 years 1 week ago. Offline
Joined: 8 Jul 2008
Posts: 87
Dear Alexandre/Dieter,
Thanks for your fast replay I mad your steps and I found the following:
Activity #1; Start 1/01/2010 8:00 Finish 10/01/2010 16:00 (calendar #A; 6 working days 8hrs/day)
Activity #2; Start 10/01/2010 16:00 Finish 15/01/2010 16:00 (calendar #B; 7 working days 8hrs/day)
Activity #3; Start 15/01/2010 Finish 18/01/2010 (calendar #A; 6 working days 8hrs/day)

Well how I can solve this problem by default without need to show hours and minutes?
Best Regards,
Abeer
Dieter Wambach
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Taher

In addition to what Alexandre wrote change your user preferences to show hours and minutes:
Edit (in the menue) --> User Preferences --> Dates --> select show hours --> mark "Minutes". Then you’ll see the mismatch between calendar and your expectations.

P6 internally calculates in hours independent from what is displayed.

Regards