Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 % complete

3 replies [Last post]
Saurabh Kumar
User offline. Last seen 11 years 17 weeks ago. Offline
Joined: 11 Dec 2009
Posts: 9
Hello everyone,

How can I get % complete on summary bar, at individual activity if I am putting some % complete its does not get summarized at top level.

Thanks & Regards,

SK

Replies

Arnold Puy
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Saurabh,

You mean the Nonlabor Units/Cost % Complete? Well, perhaps the reason is because, during the assignment of your resources the "Auto Compute Actuals" & "Calculate costs from units" is not tick.

You can perform this using global change.

Regards,

Arnold
Saurabh Kumar
User offline. Last seen 11 years 17 weeks ago. Offline
Joined: 11 Dec 2009
Posts: 9
See Arnold,

For Example if I update my non labor % complete in each activity, at the top summary bar I am not getting average of non labor % complete. How could I see them?

Regards,

Saurabh
Arnold Puy
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Kumar,

Try to allocate cost into your activities. Your programme must be cost loaded in order to roll up the % complete in the summary band.

Regards,

Arnold