Units % Complete Error

1 reply [Last post]
Ken Barrett
User offline. Last seen 14 years 4 weeks ago. Offline
Joined: 14 May 2007
Posts: 37
Basically I have a column for the Units % complete that is adding up wrong.

I have all my activities set for Completion type = to Units and individual activities units % complete are correct, but in the WBS Banding the total Unit % complete do not add up. for instance my Budgeted Labour Units for the broject = 143553 and my Actual Labour Units for the project = 59830. The Units % complete at the top of the project is saying 48.13% but if you do the math it equals 41.67%. Why is the % complete incorrect?

Replies

Mark M
User offline. Last seen 14 years 24 weeks ago. Offline
Joined: 1 Jun 2008
Posts: 33
Groups: None
Hi Ken

The calculation for Units % Complete doesn’t consider your budgeted units. It is calculated as Actual Units/At Complete Units*100, therefore, it is important that your Actual & Remaining Units are correct, to get the tool to give the right answer.

Hope that helps.

Regards
Mark