Regarding the same issue,is there any settings provided in P6 to change the default time for a finish milestone activity to commence at 6:00pm instead of 8:00 am. In my one project i changed the activity type of an activity from start milestone to finish milestone. The date then changed from 20-Mar-2011 07:00am to 20-Mar-2011 07:01 am. The same thing when i done in another project the time changed from 07:00am to 5:00 pm.Why this discrepancy? Can anyone help me in rectifying the issue please, then it would be greatly helpful.
What activity type did you assigned to Activity A.It should be finish Milestone with finish on constraint of 1Mar10. Then check the assigned calendar to your activities to correct the timings. As for Activity B, it will start using the same date and time of finish date of activity A
hiMyself Shebin.Regarding the
hi
Myself Shebin.
Regarding the same issue,is there any settings provided in P6 to change the default time for a finish milestone activity to commence at 6:00pm instead of 8:00 am. In my one project i changed the activity type of an activity from start milestone to finish milestone. The date then changed from 20-Mar-2011 07:00am to 20-Mar-2011 07:01 am. The same thing when i done in another project the time changed from 07:00am to 5:00 pm.Why this discrepancy? Can anyone help me in rectifying the issue please, then it would be greatly helpful.
Thank you
RE: Start - Predecessor activity with a finish milestone
Hi Richu,
This problem has been corrected in P6 v7.
The only solution is to change the 8:01 into 8:00 AM
Regards,
Arnold
RE: Start - Predecessor activity with a finish milestone
Hi Richu,
What activity type did you assigned to Activity A.It should be finish Milestone with finish on constraint of 1Mar10. Then check the assigned calendar to your activities to correct the timings. As for Activity B, it will start using the same date and time of finish date of activity A
Regards