Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Start - Predecessor activity with a finish milestone

3 replies [Last post]
richu rose
User offline. Last seen 3 days 9 hours ago. Offline
Joined: 13 Feb 2007
Posts: 63
Groups: None
Hi,

I have the following problem in P6:

I have assigned activity A with a finish mile stone, finishing on 01st March 10 08:01 AM (08:01 AM is the time appearing in the finish column0 .
Activity B having a duration of 03 days with activity A as the predecessor & FS relationship shows start date as 01st March 10 08:01 AM & finsh date as 04-Mar-10 08:01 AM. Is’nt this wrong.

In fact the correct finish date for activity A must be 01st March 10 06:00 PM & for activity B start date as 02nd March 10 08:00 AM & finsh date as 04-Mar-10 06:00 PM.
How do i get this right in P6.

Cheers,

Richu

Replies

Shebin Thomas
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 22 Apr 2011
Posts: 5
Groups: None

hi

Myself Shebin.

Regarding the same issue,is there any settings provided in P6 to change the default time for a finish milestone activity to commence at 6:00pm instead of 8:00 am. In my one project i changed the activity type of an activity from start milestone to finish milestone. The date then changed from 20-Mar-2011 07:00am to 20-Mar-2011 07:01 am. The same thing when i done in another project the time changed from 07:00am to 5:00 pm.Why this discrepancy? Can anyone help me in rectifying the issue please, then it would be greatly helpful.

Thank you

Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Richu,

This problem has been corrected in P6 v7.

The only solution is to change the 8:01 into 8:00 AM

Regards,

Arnold
Wilfredo Jr. Flores
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 3 Sep 2005
Posts: 32
Groups: None
Hi Richu,

What activity type did you assigned to Activity A.It should be finish Milestone with finish on constraint of 1Mar10. Then check the assigned calendar to your activities to correct the timings. As for Activity B, it will start using the same date and time of finish date of activity A

Regards