Copy of Project

4 replies [Last post]
Arun Vasanth
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Hai Friends
Nw I came with a new subject (Copy)

Before in p3 I was doing like goto>>>project utilities >>>>>
copy>>...
then I can copy the entire project in my desired location .

Why Iam askikng this question means in p3
After completing the full base program I made a copy of that programe

eg v300 my base program then I will make a copy or back up of v300 in som other location .After that I start to copy from base progarmme V301 .I used to update V301 by making V300 as base program.After one month for the monthly updation I make a copy of V301 as V302 and update V302 as V300 the base program.

My dear friends I want to do all these functions in P6 please help


With regards
Arun.V

Replies

Arun Vasanth
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Hai Arnold
Again u helped me ...

Thnxs
With regards
Arun.V
Arnold Puy
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Arun,

With P6, the solution of your problem is very simple.

How to copy a project.

1. Go to Enterprise --> Projects, highlight the project you want to copy. Simply right click then select "Copy". Right click again then select "Paste" . You can paste it anywhere you wish in the EPS node, all the check box must be marked and select OK.

2. Open the project you want copy and go to File --> Export --> Primavera PM/MM - (XER).

How to maintain and assign baseline.

1. When you finish the step #1 on how to copy a project, open your current project and go to Project Menu --> Maintain Baselines... Select "Add" you can select a "Save a copy of the current project as a new baseline" or "Convert another project to a new baseline of the current project" then select OK.

2. When done, go to Project Menu --> Assign Baselines...Now you can select a Project Baseline or User Baselines..


Regards,

Arnold



Arun Vasanth
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Thxs George
George Cabatay
User offline. Last seen 13 years 1 week ago. Offline
Joined: 31 Jan 2007
Posts: 3
Groups: None
I think you need to enroll P6 tutorial class