Calendars

1 reply [Last post]
mike mark
User offline. Last seen 15 years 42 weeks ago. Offline
Joined: 7 Jul 2009
Posts: 10
How does the project calendar and resources calendar work and which one of the calendar take preceedent over the other on a project?

How does the calendars work individually and together?

How do the calendars affect manhours and durations in P6?

Replies

Dieter Wambach
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Mark

An activity is task- or resource dependent (activity type). Depending on this entry, the activity- or the resource-calendar will be used for calculation.
The summary bars depend on the default calendar.

Dieter